Ottawa to get new LRT handover date on Thursday after RTG gets extension – Ottawa

[ad_1]

The consortium building Ottawa’s Confederation Line is expected to give the city a new date on Thursday for when it will hand over the delayed light rail transit line, after requesting an extension to come up with the new completion date.

The Rideau Transit Group (RTG) was supposed to provide the City of Ottawa with a new handover date for the $2.1-billion LRT line on Wednesday, Jan. 2, after blowing past two deadlines in 2018.


READ MORE:
No new deadline for Ottawa’s LRT in latest update from city

In a statement attributed to Michael Morgan, the city’s rail construction program director, the city said it granted the consortium a one-day extension.

“City staff will review the new date and respond to RTG. Staff will provide an update to Council following the review of the new RSA date,” the statement said.

Mayor Jim Watson and Transportation Manager John Manconi said in the fall that the Confederation Line will be in service by Mar. 31, 2019.

Once RTG hands the city the keys to the rail line, the municipality will need seven to 10 days to get the east-west Confederation train “into launch mode,” Manconi said in November.


READ MORE:
Launch of Ottawa’s LRT delayed until 2019

The original target date for the LRT’s completion was May 24, 2018. The city allowed the consortium to push that deadline to Nov. 2 without penalty.

Then, late last summer, RTG advised the city it wouldn’t make the November deadline, either. The city has penalized the consortium $1 million for the delay and said it would fine RTG another $1 million should it miss a third deadline.

In September, Watson said the city is prioritizing the safety of the 13-stop LRT system over meeting “a predetermined date in the calendar.”

WATCH: Sneak peek of the Ottawa LRT





The city is expected to report its recommendations for the winning bidders for Stage 2 of LRT — which will involve extensions to both the Confederation and Trillium lines — early this year.

In a year-end interview with Global News, Watson said in December the city hopes to have shovels in the ground for Stage 2 by the end of 2019.